Which statement about Design-Bid-Build is true?

Prepare for the Amber Book Practice Management Test with engaging multiple choice questions, detailed explanations, and study guides. Sharpen your skills and boost your confidence for the PcM exam. Get ready to ace your test!

Multiple Choice

Which statement about Design-Bid-Build is true?

Explanation:
In Design-Bid-Build, the design team finishes the drawings and specifications before any contractor is brought in, so the project is bid and constructed based on those complete documents. Because the contractor’s price and work plan rely on what’s drawn and written, anything less than thorough, well-coordinated drawings can lead to change orders during construction. That’s why having drawings as complete and detailed as possible early is the best way to manage the risk and impact of changes. The other statements don’t fit: DBB typically doesn’t shorten the schedule because design, bidding, and construction happen in sequence; change orders are not rare or “almost impossible” in practice; and design documents are essential, not something the method eliminates.

In Design-Bid-Build, the design team finishes the drawings and specifications before any contractor is brought in, so the project is bid and constructed based on those complete documents. Because the contractor’s price and work plan rely on what’s drawn and written, anything less than thorough, well-coordinated drawings can lead to change orders during construction. That’s why having drawings as complete and detailed as possible early is the best way to manage the risk and impact of changes. The other statements don’t fit: DBB typically doesn’t shorten the schedule because design, bidding, and construction happen in sequence; change orders are not rare or “almost impossible” in practice; and design documents are essential, not something the method eliminates.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy