In base Design-Bid-Build contracts, which pair correctly matches the AIA document to the party?

Prepare for the Amber Book Practice Management Test with engaging multiple choice questions, detailed explanations, and study guides. Sharpen your skills and boost your confidence for the PcM exam. Get ready to ace your test!

Multiple Choice

In base Design-Bid-Build contracts, which pair correctly matches the AIA document to the party?

Explanation:
Design-Bid-Build relies on separate contracts for design and construction. The agreement with the architect is the Owner-Architect Agreement, B101, which governs the architect’s services from concept through construction administration. The agreement with the contractor is the Owner-Contractor Agreement, A101, which governs the construction work between the owner and the contractor. Since DBB keeps design and construction as distinct contracts, the correct pairing is B101 with the owner-architect and A101 with the owner-contractor. This setup reflects the process: first hire the architect to design, then hire a contractor to build after bidding, under separate agreements.

Design-Bid-Build relies on separate contracts for design and construction. The agreement with the architect is the Owner-Architect Agreement, B101, which governs the architect’s services from concept through construction administration. The agreement with the contractor is the Owner-Contractor Agreement, A101, which governs the construction work between the owner and the contractor. Since DBB keeps design and construction as distinct contracts, the correct pairing is B101 with the owner-architect and A101 with the owner-contractor. This setup reflects the process: first hire the architect to design, then hire a contractor to build after bidding, under separate agreements.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy